- Technical
The effort required to achieve the JIP objectives has been grouped into
tasks, these are described by section below:
1. Preparation for Field Trials
Objective:
To prepare and qualify the OIWM for safe and reliable use in a field
trial
Fouling
During the CoSWaSS trials a coating of corrosion products and salt
deposits partially obscured the optical window and promoted oil
filming. The coating caused a change in the response of the OIWM
to oil concentration during the tests. Two methods of correcting
for the presence of fouling were devised, one used signal analysis
to correct the OIWM measurements and the other used maintenance
intervention to physically clean the window area.
A short study funded by CoSWaSS is currently ongoing which is due
for completion end September 2001 which will recommend one or more
optimum technologies. Further investigation of the types of fouling
likely to occur and methods of prevention or removal will be required
to define and implement the best solution(s) for the OIWM. The investigation
will identify the most prevalent types of fouling and the strategies
which may be used to prevent the fouling, or to remove the fouling
from the optical window. Help will be sought from participants in
providing data on types and quantities of fouling/ scaling encountered
in practice and in accessing existing emerging technologies. Once
the most appropriate anti-fouling technology has been identified,
it will be implemented in an OIWM for a field trial.
Concentration Algorithm
During the CoSWaSS trials the influence of various parameters, such
as temperature, pressure and produced water salinity on the OIWM
response were characterised. Resulting from this characterisation
a prototype algorithm for predicting the oil concentration in a
produced water stream has been derived. The algorithm will be further
refined, implemented into the OIWM software and then tested during
the field trial.
Field test site
Suitable test sites will be sought from the project sponsors from
the start of the project. During this stage in the project the best
match to the requirements will be identified. As part of this process
the deviations between the OIWM specification and the test site's
required standards will be identified, and a work package to carry
out any required modifications will be specified. A draft specification
for a field trial site is attached as Appendix 2.
OIWM modifications
The specified OIWM modifications, expected to at least require qualification
of the OIWM prototype for hazardous area use, will be made during
this task. Other required changes, such as the addition of a modem
to permit remote access, will be made simultaneously. Once the modifications
and qualifications have been achieved, the OIWM will be re-built
and characterised in readiness for a field trial.
2.
Field Trial 1
Objective: Determine the effectiveness of the anti-fouling technology
and the suitability of the OIWM for field use
The trial will be planned for a six month duration on a topsides produced
water re-injection or discharge line. Following installation and commissioning
the topsides prototype OIWM will be left to be run by the site operations
group, with data analysis and support provided by KOP throughout the
trial. A report will detail the performance of the system during the
trial and describe any improvements required prior to qualification
of the final OIWM design.
3. OIWM modifications
Objective: Implement changes which are required as a result of
the field trial and concurrent design work; re-build and re-characterise
in readiness for a further field trial.
It is anticipated that some modifications may be required to improve
the OIWM performance in combating fouling and scaling, or in other
functional aspects. As it is not possible to define these changes
prior to the field trial, the cost of this segment of work is estimated.
4. Subsea OIWM design
Objective: A specification for the subsea OIWM will be produced,
and this will form the basis for the subsea design package.
The design of the OIWM will be largely common between topsides and
subsea versions. A basis of design will be formulated for the OIWM
and will cover the requirements for topsides, subsea and down-hole
versions of the instrument. From this overall basis of design the
subsea specification will be produced. The design work for the subsea
OIWM is anticipated to fall into three main categories; system and
electronics design; software design; and packaging design.
Electronics and system design
As a result of the testing carried out on the CoSWaSS OIWM, some
of the current electronics may be redundant. If significant redundancy
can be identified there will be benefits to reliability in simplifying
the system design. In addition there may be significant benefits
to be gained in re-design of some system components for the subsea
OIWM to improve reliability and to reduce the size and weight of
the packaging required.
Software design
Good software design is critical to the reliability and successful
operation of subsea instruments. The software will be split into
modules allowing operation of the OIWM in different modes. These
modes will allow zero calibration, normal operation and software
download so that should software up-grades become available these
can be downloaded into the in-situ instrument. The software will
be ported onto the KOP standard subsea operating system and will
provide an interface compatible with subsea control modules.
Subsea packaging design
As part of the marinisation process the OIWM will be packaged into
a suitable containment for subsea application. The containment has
to fulfil key criteria as defined in the basis of design. The containment
will protect the instrument from the external environment, maintain
a stable internal environment and ensure that temperature fluctuations,
shock and vibration do not adversely affect the integrity of the
instrument. The experience which KOP has accumulated over many years
of designing, building and deploying subsea electronics will be
used to ensure the highest standard of design for the subsea OIWM.
The qualification procedure against which the subsea OIWM will be
tested to prove its design will be defined against the basis of
design. The subsea OIWM will be tested against the qualification
procedure to ensure the integrity of the instrument is adequate
for subsea use.
5.
Field Trial 2
Objective: Determine the effectiveness of the modifications to
the OIWM following the first field trial. Feed in any design improvements
required prior to finalising the design of the subsea OIWM as the
trial progresses.
The trial will be similar to the first field trial, planned for a
six month duration on a topsides produced water re-injection or discharge
line. Following installation and commissioning the OIWM will be left
to be run by the site operations group, with data analysis and support
provided by KOP throughout the trial. A report will detail the performance
of the system during the trial. It is proposed that the unit used
will still be the topsides OIWM since subsea design and implementation
will not be complete before the start of this trial - although the
steering group may determine any changes as the project progresses.
6. Qualification
Objective: Qualify the subsea OIWM for immunity to environmental
factors which may adversely influence its performance and for performance
in measurement of oil in water
Environmental
qualification
Once equipment is deployed subsea it becomes very time-consuming and
expensive to retrieve for repair or modification. Because of this
the qualification of equipment is of prime importance. The subsea
OIWM will be put through similar qualification tests to other KOP
subsea electronics. The tests will cover operation at low and high
temperature extremes, thermal cycling, storage at low and high temperature
extremes, operation during various vibration modes, shock testing,
pressure and hyperbaric testing. The subsea OIWM interfaces to control
systems will also be verified and the OIWM will be qualified by testing
against relevant EMC directives.
Duty qualification
Following completion of the environmental qualification, the subsea
OIWM will be put through a qualification process to ensure that the
instrument's capability to measure oil in water concentration has
not been diminished by any design changes. The qualification will
characterise the OIWM responses to temperature, pressure and produced
water salinity and ensure these match with previous versions of the
instrument. Following completion of the characterisation the OIWM
will be qualified for stability and repeatability. The final qualification
test will be a flow test in oily water to define the measurement performance
of the subsea OIWM.
|